Commissioners Advance Outlying Fields Plan on 5-0 Vote

Escambia County Commission

Final Hearing Set for Nov. 5

Beulah residents warn the developer’s rewrite of the DPZ design code abandons the walkable town the community asked for. The applicant says the changes are inches, not miles.


The Escambia County Board of County Commissioners voted 5-0 on Thursday, Oct. 15, to move forward an ordinance adopting the Outlying Fields (OLF) Master Plan, Design Code, Regulating Plan Map and Road Classification Plan. The property is also known as OLF-8. The ordinance amends Chapter 3, Section 3-1.3 of the Land Development Code, “Zoning and Future Land Use,” and sets permitted uses and site and building requirements for the Beulah property.


What the Board Did


The Critics’ Case

The hearing record I have begins in the middle of public comment, so I can only report on the speakers captured in the transcript. The most detailed critique came from Beulah resident Theresa Blackwell, who argued that the applicant’s design code “will dismantle the heart” of the DPZ master plan the county adopted after years of public engagement.

Blackwell said the rewrite:

She also read from a letter by Marina Khoury of DPZ, the original master plan firm. Blackwell said Khoury accused the applicant’s planner of misrepresenting the adopted code and called the process “shameful and demoralizing.” In that account, the rewrite moves OLF-8 from form-based, walkable mixed use to conventional suburbia.

“Just trust me is a recipe for failure.”


The Applicant’s Answers

Chair Ashlee Hofberger held the applicant to the end of the public comment period so the team could respond to every concern raised. She told the room they would get as much time as needed to answer the questions. Attorney Troupe Brewer of Phelps Dunbar, representing Tri-W Development, the purchaser under the county contract, took the podium. Tri-W is a joint venture of Chad Henderson of Catalyst HRE and Jim Wilson and Associates. He also answered a list of written questions from Vice Chairman Stroberger. The key points:


What the Answers Left Open

The applicant’s team did not directly address three of Blackwell’s specific charges: the removal of agriculture from residential areas, the claim of nearly double the possible density, and the figure of two additional stories. Brewer said only that maximum building heights “are changed.”

 


Commissioners Weigh In

Stroberger said the developer team was not his first choice, but that “you won me over.” He said he asked the developers to talk to Navy Federal and to Blackwell, and that they did. He described a campaign sign dispute on the property and said he had “every reason not to want this to happen.”

“I didn’t have the votes here, so I found another way to try to help manage this.”

Stroberger also turned on Blackwell, saying she had taken more private meetings with the developer than anyone else, including him, and asking why she was taking the matter so personally. He urged residents to ask the kind of questions he had asked rather than make accusations about the relationships among the board, the county, the developers and the attorneys.

Kohler said the board went through a series of bidders before narrowing to  Tri-W Development, and that he backed the team because it did what it said it would do. He said he did not like the county keeping 171 acres, but sometimes you have to accommodate.


The Money

Chad Henderson of Catalyst HRE, a partner in Tri-W Development, told the board the county’s investment in the property was roughly $17 million. The county sold 100 acres for $4 million, leaving a basis of about $13 million. He said the proposed plan would more than double that by selling a portion of the property while the county keeps the largest district for economic development and job creation.


The Bottom Line

The vote was never in doubt once Stroberger and Kohler spoke. The real test is Nov. 5 —the second and final hearing.