Airport Director Matt Coughlin on the $165M Overhaul, ST Aerospace’s Boom—and Pensacola’s Vegas Obsession

Pensacola International’s director sat down with me on this week’s episode of Rick’s Blog Live to talk terminal construction, Breeze Airways’ explosive growth, and the one route everybody keeps asking about.


Pensacola International Airport Director Matt Coughlin has been on the job since 2020, and he told Rick the airport’s growth has outpaced its infrastructure—which is exactly what the airport’s $165 million modernization program is meant to fix. That figure covers the terminal area and concourse alone; the aircraft ramp work adds even more to the bill.

Expected completion: about two years out, though Coughlin cautioned the 100% design phase will produce a more refined schedule.

What Flyers Will Actually Notice

Coughlin was candid about the disruption ahead:

The security checkpoint is getting a full reorientation—rotating 90 degrees and doubling in footprint, with glass walls overlooking the airfield. On the other side, travelers will choose between the current Concourse A and the brand-new Concourse B.


ST Aerospace Continues Growing

Beyond the terminal, the airport’s ST Aerospace hangar campus keeps expanding. The third hangar is fully built, with ramp infrastructure now going in; Coughlin expects full production there by January. Construction has already started on a fourth, smaller hangar.

By the numbers:
7 airline partners • 28 nonstop destinations • Breeze Airways grew from 2 weekly Tampa flights to 30+ destinations in under two years

Now, About That Vegas Flight…

Pensacola’s number one underserved market, according to Coughlin, is out west—and everybody knows what that really means: Las Vegas.

“We were close, but fuel had kind of curtailed that for a little bit. We’re gonna pursue that.”