Rick's Blog

June CMPA budget: $4.5 million soft costs to complete

The June 30 budget for the Community Maritime Park showed the current construction contract with Magi at $39,284,704. The total cost for the work left to be done was $8,116,530 – increasing Magi’s contract to $47 million. The breakwater had been deleted because that it could be done cheaper than through Magi.

Then added to the budget:

Scoreboard, FF&E, AV & Concessions: $2.15 million

Developer & CMPA soft costs:$4.5 million

This got the total project to $54,051, 054, which leaves a $490,175 over the budget.

 

The question is what kind of soft costs hit the project of $4.5 million over the next six months?

 

Here is the budget: CMP June 30 2011 Budget

 

 

 

 

Exit mobile version