Three Years, Multiple Studies, and Still No Approved Bay Center Plan

Accountability | Escambia County Commission, Mayor D.C. Reeves

Since 2023, the Escambia County Commission has heard at least a half dozen presentations on renovating the Pensacola Bay Center. The only formal vote I can find is a $10 million maintenance package in May 2024.


The Escambia County Board of County Commissioners has spent nearly three years discussing how to fix the aging Pensacola Bay Center, and the public record shows one formal vote.

Here is what the record shows, and what remains unanswered as a new board takes office.


The timeline

2023: The building gets a physical. A facility condition assessment found the arena “generally in ‘Fair’ condition overall with isolated elements in ‘Poor’ or ‘Failed’ condition.” I could not confirm the date it went to commissioners.

March 2024: More study, more money. The Pensacola News Journal reported that the assessment estimated about $72.5 million in needs over seven years and nearly $140 million over 20. Commissioners agreed to pay Populous Inc. an additional $49,000 to refine those numbers. County Administrator Wes Moreno said the county wanted to keep working with ASM Global and reduce the Bay Center subsidy. No timeline was set for funding decisions.

Spring 2024: The one vote. WKRG reported that commissioners approved $10 million for Bay Center improvements over four years, paid from the tourist development tax. The schedule: $3 million in year one for sound, lighting, parking lot repaving, fencing and retractable seating; $3,011,000 in year two for the end-of-life ice plant; $2,310,000 in year three; and $1,670,200 in year four.

August and September 2024: A $90 million idea. The Tourist Development Council (TDC), which only recommends, heard a proposal for up to $60 million for an indoor sports facility at Ashton Brosnaham Park and $30 million in tourist tax money for the Bay Center. The TDC recommended it in September. Final decisions belong to the commission. At the time, a TDC member questioned spending $43 million on upgrades without an outside physical study.

March 6, 2025: ASM Global pitches $47 million. At a Committee of the Whole meeting, ASM Global presented renovation concepts of about $47 million and asked for a two-year contract extension. It offered up to $200,000 for feasibility and design studies if it got the extension. Commissioners directed staff to draft an addendum. No vote was taken at the meeting.

April 2025: Four options. NorthEscambia.com reported the commission had considered four concept designs ranging from $22 million to $104 million for the Bay Center alone.

April/May 2025: Pensacola Mayor D.C. Reeves injects himself into the commissioners’ discussions. He asked the county to collaborate on a comprehensive plan for renovating the Bay Center and possibly developing the surrounding area. The city would pay for a district master plan, and he suggested a joint meeting at City Hall within 30 to 45 days to pick a planning firm. Reeves then pushed for a joint city-county task force, and Kohler responded with a resolution for an 11-member advisory committee.

July 10, 2025: A joint workshop with the city. Chair Mike Kohler and Mayor D.C. Reeves said they wanted to move quickly. According to my report on the meeting, $25 million was already committed through a bank loan and about $75 million remained in bonding capacity. Kohler warned that state legislation could affect tourist tax dollars if the project was not advanced by July 1, 2026. The decision on a citizen advisory committee was postponed, and no formal votes were taken.

January 23, 2026: The $189 million plan. Legends Global, the Bay Center’s operator, presented a market and feasibility study. The package totaled $189 million, including $71 million for arena renovations. Consultants projected $59.2 million in total annual economic impact. WUWF reported that commissioners did not take a final vote.

April 16, 2026: A consensus, but no vote. At a joint meeting with the Pensacola City Council and the mayor, the numbers on the table were about $71 million for the renovation, $84 million to $86 million for a new event center, and about $30 million for a second ice sheet. Commissioner Steven Barry estimated bonding capacity at about $150 million. Chair Ashlee Hofberger summarized the direction: renovate, add an event center, keep negotiating a public-private deal on the second ice sheet, and have the city handle parking. The meeting produced no vote.

August 6, 2026: A smaller first phase. At another Committee of the Whole workshop, staff recommended a phased approach starting with a roughly $74 million first phase to renovate the existing building. Staff will prepare a request for proposals to find a long-term private development partner. WUWF reported that no votes were taken.

November 17, 2026: A new board. Joe Vinson and Mike Kohler were sworn in, with Vinson replacing Hofberger in District 4. The new board inherits an unapproved first phase and an unsettled agreement with the city.


What the record raises


Where this stands. The Bay Center opened in 1985, and the county has now spent three years studying what to do with it. The commission has the tourist tax money and a consensus on direction. What it does not have is a vote on a plan.