Even Kevin White gets it
ECUA approve the Dale Perkins 5 Point 3 Point Plan yesterday, 3-2. Perkins, McCovery & Walker voted for Fort Perkins. Benson and Fink voted “No.”…
Tell ECUA Board to move Main St. Plant….no more games
Call or email (click on names for email addresses) Chairman Mr. Logan Fink District One (850) 944-1941 Term expires November 2008 Vice Chairman Mr. Elvin…
Plans for Fort Perkins revealed
ECUA board member Dale Perkins has told us that if the city and county don’t fork over $38 million each then he plans to fortify…
Perkins has done this before
In 2001, ECUA, DEP and International Paper were working an agreement for $92 million project to build a pipeline that would take IP’s wastewater away…
ECUA/Dale Perkins plan is extortion scam
In the PNJ (ECUA to review funding plan), the ECUA Board still refuses to pay for the entire $115 million with its Dale Perkins five-point…
How to raise $115M to move ECUA plant
See if you can follow my math: Funds needed $115,000,000 Interest (30 yrs, 5.25%) $153,000,000 Closing costs (est) $ 4,740,000 Total needed $272,740,000 _________________________________________________ The…
ECUA manages on a prayer
Yesterday’s PNJ article on the relocation of the Main Street Sewage Treatment plant ( Anyone got $115 million? ) really bothers me, especially this section:…
IN: Aftermath of Hurricane Ivan
Hurricane Ivan kicked us out of our nice digs in the Theisen Building. We left half our furniture behind – either destroyed or it was…
Does ECUA get the message?
 One government agency that should listen hard to the Sept. 5th primary vote is the Emerald Coast Utility Authority. The voters want change. We…