American Creosote Superfund: Phase One Begins in December

Environment

Pensacola has secured more than $50 million in additional federal and state funding for the American Creosote Works (ACW) Superfund site over the past 12 months, Mayor D.C. Reeves announced at his press conference this morning, citing new commitments from the EPA and Florida DEP that fully fund phase one of the cleanup and cover a large share of phase two.

“Within the last 12 months, we’re over $50 million of additional funding that wasn’t there, thanks to DEP and EPA,” Reeves said.

Background: The 18-acre American Creosote Works Inc. (Pensacola Plant) Superfund site is located on 701 J Street in Pensacola, Florida. It includes the area where a wood-treating facility operated from 1902 to 1981.

Two Phases

Phase one funding gap closed. The city had faced roughly a $9 million shortfall to fully fund phase one. Reeves credited EPA, along with several trips to Washington, D.C., with closing that gap.

Phase two funding largely secured. EPA confirmed Tuesday night that phase two, estimated at $68 million total, now has a cost-share agreement between DEP and EPA covering $48.4 million of that work. Phase two includes:

By the numbers

$50M+

in new federal/state funding secured in the past 12 months

$9M — phase one gap now closed
$68M — total estimated cost of phase two
$48.4M — DEP/EPA cost-share commitment toward phase two

What’s still open: The remaining balance of phase two funding, roughly $19.6 million, is not yet secured. Reeves said the city will keep working to close that gap, but the immediate priority is getting phase one underway in December.

 