Pensacola Dysfunction Junction: Tanyard Day Six

Sorry to report, no change at in Tanyard neighborhood near the Mayor Ashton Hayward’s Government Street Stormwater Project, which is being construction only two blocks west of City Hall.

The filtration system is blocking Coyle Street. No fencing has been placed around the pond. The side streets are muddy and dirty.

According to the only letter that the City sent the Tanyard residents, the project was to be completed on Sunday, Dec. 18.

Share:

Author: Rick Outzen

Rick Outzen is the publisher/owner of Pensacola Inweekly. He has been profiled in The New York Times and featured in several True Crime documentaries. Rick also is the author of the award-winning Walker Holmes thrillers. His latest nonfiction book is “Right Idea, Right Time: The Fight for Pensacola’s Maritime Park.”